Елена Макарова Управление Рисками

Main summary

Key takeaways

Business

Topic: Risk management for digital/data-driven projects (corporate & public-sector examples)

  • Frames risk management as a long-established corporate practice to improve project effectiveness.
  • Core idea: Higher risk → higher project cost (e.g., hedging via discount/interest rate; banking/infrastructure cost increases).
  • Defines risk as: the probability of an event that can be negative or positive and can significantly affect project outcomes.
  • Emphasizes that risk has:
    • Source
    • Consequences
    • Multiple characteristics tied to likelihood and impact on key project components

Risk management system (iterative process / stages)

1) Risk identification (most important step)

  • Goal: produce an identified list of risks.
  • For a “good project” aim for ≥ ~50 risks (practical note: often 10–15 are easy early; then it gets harder).

  • Each risk must be captured using 4 fields:

    • Risk name
    • Cause
    • Trigger (symptom)
    • Consequences
  • Quality rule: the consequences must not be the same as the risk name (avoid duplicate wording/sound → indicates incorrect structuring).

  • Practical goal illustrated for a workshop example:

    • Start with fewer (e.g., 25) and “in real life” strive for ~50.

2) Risk assessment

  • Quantify/qualify each risk using two indicators:
    1. Probability of occurrence
    2. Degree of impact on significant project indicators
  • Outputs: a risk matrix (probability vs. impact) to identify most critical risks.

3) Monitoring & control

  • Iterative updates based on:
    • Whether triggers/symptoms indicate probability has changed
    • Whether the risk is closer or farther due to internal/external environment changes

Management ownership

  • Risk management is described as the prerogative and personal responsibility of top management (project/process/department leadership).

Risk sources: internal vs external

External risk sources

  • Legislative changes
    • Example: recent Russian legislation changes increased risks (e.g., pension reform, social/economic risks).
    • Example of positive legislative impact: reduction in Russia’s key rate by >1 percentage point; last reduction mentioned: -1.5 pp, reducing cost of capital and benefiting the economy.
  • Market reaction to new products/technologies
    • New offerings can force companies without flexibility into overstocking, higher financial burden, and loss of competitiveness.
  • Competitor actions and technological shifts.
  • State-level example: Shale oil & gas appearing (~2013 context)
    • intercepted sales and buyers
    • logistics changes via liquefied gas technologies
    • spillover effects mentioned:
      • real income decline
      • ruble value effects

Internal risk sources

  • Human capital/competence gaps
    • Digital economy/data workflows: lack of capacity to analyze large information volumes → incorrect conclusions/final results.
  • Project-area inherent risk
    • Example: oil production/refining risks due to long cycle (up to ~15 years) → world and consumer conditions can change significantly.

Impact model: what risk affects

Risk consequences ultimately distribute across four project components:

  • Goals / target indicators
  • Cost
  • Quality of results
  • Timing / deadlines

Triggers (risk signs / symptoms)

  • Trigger = an observable change/event indicating probability of a risk is sharply increasing.
  • Example (construction fire):
    • Risk: “fire”
    • Possible causes: safety violations, poor-quality wiring
    • Rejected trigger example: “smoke appears” is too close to the fire itself
    • Better trigger examples:
      • workers smoking on-site improperly
      • frequent/increasing short circuits detected during inspections

Correlation/synergy between risks (combined effects)

  • Instruction: don’t treat risks independently.
  • If 2–3 risks trigger simultaneously, they can create synergistic effects (positive or negative).
  • Example chain (Russia/oil & gas context):
    • emergence of shale oil/gas
    • sanctions after Crimea annexation (2014)
    • later lifting/changes in sanctions (e.g., Iran mentioned) → increased supply → downward pressure on prices
    • demand not fully recovering after 2008–2009 crisis
    • resulting interconnected pressures on market and effective demand; downstream effects cited like price collapse (e.g., $140 → ~$35–40 as a historical illustration)

Methods/playbooks for risk identification (practical toolset)

Used in parallel; encouraged to apply multiple methods for better coverage.

  • Review of project documentation
    • Check contracts/specs/tender docs/technical requirements for contradictions that reveal risks.
  • “Hypothesis from the opposite” / reverse hypothesis
    • Build an initial hypothesis of what the project will achieve.
    • Then reason from the opposite outcome (“if it doesn’t happen—why?”) to generate risks.
    • Example: high-speed rail promised passenger growth; if flows don’t rise and complementary infrastructure doesn’t develop → risks like routing choice, pricing too high, or wrong transport mode selection.
  • SWOT analysis (risk-oriented, not only formal)

    • Quadrants: Strengths, Weaknesses, Opportunities, Threats
    • Suggested approach: create ~5 items per quadrant → derive multiple risks.
    • Caution: avoid “SWOT as paperwork”; use it strategically (use strengths to capture opportunities; address weaknesses/threats).
  • Brainstorming

    • Pros: cheap, flexible.
    • Cons: difficult to gather experts; conflict of interest, hierarchy suppression, and needs strong moderation (otherwise becomes “a bazaar”).
  • Expert inquiry with sociologists (iterative remote questionnaires)
    • Designed to mitigate brainstorming downsides:
      • interview large expert groups
      • multiple rounds
      • sociologists refine questions between iterations
    • Drawbacks: high cost (noted “from millions of rubles”).
    • Incentive challenge: motivate experts to respond (status/complexity + possible monetary rewards).
  • Visualization / Ishikawa (fishbone) diagram
    • Break the process into stages (example categories mentioned):
      • machinery/equipment
      • human resources
      • incoming raw materials
    • Identify bottlenecks at each stage and link to defect/final outcome causes.

Risk assessment mechanics (scoring & matrix)

Qualitative scoring

  • Probability rated on a 5-point scale:
    • “Very high”, “High”, “Medium”, “Small”, “Rarely encountered”
  • Guidance: scoring should involve experts.
  • Warns against simplistic 50/50 guessing:
    • if unknown, probability rankings become unreliable (illustrated with the “dinosaur probability” joke).

Impact scoring

  • Impact degree divided into 4 significant characteristics:
    • effect on cost
    • effect on goals/targets
    • effect on timing
    • effect on quality
  • Mentions using the arithmetic mean from these ranks to form an overall impact score.

Risk matrix output

  • Create matrix:
    • Vertical: probability rank
    • Horizontal: impact rank
    • Cells contain the ordinal numbers of risks at intersections
  • Prioritization:
    • Most important risks cluster in the upper-right quadrant (high probability + high impact).
    • Suggest choosing ~7 top risks (if total is 20/25) for detailed personal response strategies.

Risk response strategies (action playbook)

For each top risk, define a response strategy (options from negative to positive):

  1. Accept
    • Do nothing in advance except monitor triggers/symptoms and track probability changes.
    • Note: acceptance still involves acknowledging the risk cost/treatment in planning.
  2. Transfer
    • Shift responsibility/cost to contractors via tender/subcontracting documentation.
    • Contractor includes risk response funding internally.
  3. Minimize
    • Reduce likelihood and/or consequences:
      • Example: fire risk → increase inspection of wiring to reduce likelihood; use less flammable materials and enforce cleanliness/safety to reduce consequence severity.
  4. Avoid / abandon
    • In rare cases when risk makes continuing the project pointless, reconsider or abandon the initiative and revise conditions.

Positive risks (explicit reminder)

  • The speaker encourages assuming at least a couple positive risks to broaden the development horizon and improve opportunities capture.

Actionable recommendation / exercise

  • Encourages viewers to:
    • Generate ~2025 risks for a current activity (wording suggests risks for a planning horizon)
    • Build a risk impact interaction matrix
    • Use it practically for risk management implementation

Presenters / sources

  • Presenter: Елена Макарова (as indicated by the video title snippet: “Елена Макарова Управление Рисками”)

Rate this summary

Your feedback will help improve summaries.

Improve this summary

Reprocess with a stronger model when the summary feels incomplete or inaccurate.

Pro

Translate summary in another language

Pro

Ask questions to this video

Chat for follow-up questions, clarifications, and source-backed answers.

Coming soon

Share this summary

Original video